As of April 27, 2020, the permanent and surge project moves for The Office of the President, Student Affairs, and Academic Affairs are:

The Office of the President: (Halted Pending Shelter in Place Orders are Lifted)

  • The President's Office, Strategic Communications and Advancement will be moving out of Stevenson Hall to Salazar Hall 2nd Floor (old Admissions and Records suite), approximately October 2020.

Student Affairs:  (Complete)

  • DSS - Disability Services for Students,  permanently moved from Salazar Hall 1st floor to Schulz Information Center (South), May 2019.
  • Advising and Transfer Center, permanently moved from Salazar Hall 1st floor to Schulz Information Center (North), August 2019.
  • MAVRC - Military and Veterans Resources Center,  permanently moved from Salazar Hall 1st floor to Schulz Information Center (North), August 2019.
  • C.A.A.S.E. - Center for Academic Access and Student Enrichment, permanently moved from Salazar Hall 1st floor to Schulz Information Center (North), August 2019.
  • CAPS - Counseling and Psychological Services, permanently moved from Stevenson Hall 1st floor to modular unit Building 17-A (East of Salazar Hall), January 29, 2020.

Academic Affairs: (Halted Pending Shelter in Place Orders are Lifted)

  • Faculty Resource Center for Teaching and Learning,  permanently moving from Schulz Information Center 2nd floor to Salazar Hall 1st floor Suite 1060, Summer 2020.
  • Enrollment Services - Office of the Registrar and the Office of Admissions,  permanently moving from Salazar Hall 2nd floor to Salazar Hall 1st floor Suite 1071, February 24, 2020.
  • Center for Community Engagement,  permanently moving from Schulz Information Center 1st floor to Salazar Hall 1st floor Suite 1053, February 24, 2020.
  • Office of Research and Sponsored Programs,  permanently moving from Schulz Information Center 2nd floor to Salazar Hall 1st floor Suite 1040, Spring Break 2020.
  • Visitors Center - Campus Tours and Pre-Admissions,  permanently moving from Student Center 1st floor to Salazar Hall 1st floor Suite 1010, Spring Break 2020.
  • Office of the Provost, Faculty Affairs, Office of Reporting and Analytics, temporarily moving from Stevenson Hall 1st floor to Salazar Hall 2nd floor A&F Suite, Summer 2020.  
  • Academic Affairs Scheduling, temporarily moved from Stevenson Hall 1st floor to Salazar Hall 2nd floor A&F Suite, Complete.
  • The School of Extended Education, (International Education remaining in international Hall),  permanently moving from Stevenson Hall 1st floor to Sonoma Mountain Village - (SoMo Village), Summer 2020.
  • Academic Senate Office, temporarily moving from Stevenson Hall 1st floor to Schulz Information Center 3rd floor (North), Summer 2020.
  • Schools of B&E, Education and Social Sciences - deans office, faculty and staff, temporarily moving from Stevenson Hall to Schulz Information Center 2nd floor (South and North) and 3rd floor (North), Summer through September 2020.
  • Stevenson Hall, Construction will start approximately October 2020 through July 2022.
  • CFA - California Faculty Association:

  • CFA - California Faculty Association, temporarily moving from Stevenson Hall 3rd floor to Schulz Information Center 3rd floor (North), Summer 2020.